Supreme Court Rejects 50% Cut in Dredging Contractor’s Arbitral Award, Says ‘Shocking the Conscience’ Is Not Enough

The Supreme Court has restored an arbitral award in favour of dredging contractor Marino Dredgeco after ruling that courts cannot reduce compensation merely because the amount awarded for additional work appears disproportionately high compared to the original contract value.

A Bench of Justice JB Pardiwala and Justice K Vinod Chandran set aside a Calcutta High Court judgment that had slashed the contractor’s arbitral award by 50%, holding that such interference was not justified under Section 37 of the Arbitration and Conciliation Act, 1996.

The High Court had considered the additional-work claims excessive because they exceeded 70% of the original contract value. It had concluded that the amount awarded shocked its conscience and consequently reduced the compensation and interest payable to the contractor.

Disagreeing with this approach, the Supreme Court observed that describing an arbitral award as shocking to the conscience cannot, by itself, justify judicial interference. There must be a substantive reason demonstrating a clear conflict with the most fundamental notions of morality or justice.

The dispute originated from a dredging contract awarded by the Kolkata Port Trust to Marino Dredgeco for developing an approach channel and basin at Sagar Island for a pilot station.

During the execution of the project, repeated dredging became necessary because of siltation, adverse weather conditions and differences between the actual soil conditions and the information initially supplied by the Port Trust.

The Port Trust also assigned additional work to the contractor through a letter dated July 19, 2000.

After completing the work, Marino Dredgeco submitted additional bills, which eventually became the subject of arbitration. The arbitrator accepted the contractor’s claims and awarded the amounts sought.

The award was subsequently upheld by a Single Judge under Section 34 of the Arbitration and Conciliation Act. However, a Division Bench of the Calcutta High Court, hearing an appeal under Section 37, reduced the award by half, primarily because the additional-work claims exceeded 70% of the original contract value.

Challenging this reduction, Marino Dredgeco approached the Supreme Court.

Allowing the appeal, the Bench observed that the additional work essentially involved re-dredging the same channel and basin created under the original agreement. The contractor had undertaken the additional work to maintain the channel’s operational condition.

The Court noted that the High Court had focused on the financial magnitude of the additional claims without properly examining the nature of the work involved.

It also pointed out that the arbitrator had considered documentary evidence, including records of joint measurements undertaken for the additional work entrusted to the contractor.

The Supreme Court observed that the Division Bench had neither examined the measurements nor the invoices before reducing the award. Such an exercise would, in any event, amount to an assessment of the merits of the dispute, which is not permissible within the limited scope of Section 37.

The Bench further clarified that the additional dredging work could not be arbitrarily divided into valid and invalid components when the claims arose from the same nature of work.

Emphasising the limits of appellate interference in arbitration matters, the Court held that the expression ‘shocking the conscience’ cannot be invoked as a mere formality. A court must identify a concrete and legally sustainable reason establishing that the award violates fundamental principles of morality or justice.

The judgment reiterated that Section 37 does not provide appellate courts with an unrestricted power to reassess evidence, reconsider contractual claims or substitute their own conclusions for those of the arbitrator.

Accordingly, the Supreme Court set aside the Calcutta High Court’s decision and restored the arbitral award in favour of Marino Dredgeco.

Share this story